PARK ROAD UPGRADE WORKS TIMELINE AI046015

Question: Councillor B. Dennehy

“To ask the Chief Executive to provide the anticipated timeline as to

when site works will commence as well as an estimate on the length

of time required for construction of the Park Road upgrade which is a

welcome and badly needed infrastructural project in Rush while taking

into account the recent positive progress of the project in the CPO

process via An Bord Pleanala.”

Reply:

Tender documents have been prepared by the engineering consultant for

this scheme and are currently being reviewed by Fingal County Council.

The Compulsory Purchase Order is expected to be confirmed by Fingal

County Council by Q1 2019 and the tender will be issued during this time

also, with construction commencing in Q2 2019 with an expected contract

duration of six months.