top of page
Writer's pictureCllr Brian Dennehy

To ask the Chief Executive for a delivery date of the CPO required for the lands need to deliver the

COMHAIRLE CONTAE FHINE GALL

FINGAL COUNTY COUNCIL

BALBRIGGAN/SWORDS AREA COMMITTEE MEETING

(Services B – Strategic & General Matters)

THURSDAY 8th FEBRUARY, 2018

ITEM NO. 54

CPO PARK ROAD, RUSH. AI041103

Question: Councillor B. Dennehy

"

"

Reply:

The land-take for the Park Road is currently being assessed and will be

determined in the coming weeks. Once this phase is complete, the Council

will be in a position to determine the delivery of the CPO. With the specific

land-take determined, it is the intention of the Property Section of the

Council to commence the CPO process by forwarding the required

documentation to An Bord Pleanala. The CPO process will have duration

of 3 weeks, if no objections are received, at which stage the CPO can be

determined. Should an objection be received then the time scale will

extend to allow ABP to hold an oral hearing on the matter. Once this CPO

process is finalised, the Council will be in a position to update the

members on the schedule of works that will see the Park Road upgrade

works brought to completion.