To ask the Chief Executive to confirm that the Rush Sewage Network Scheme is now completely serviced

  • Writer: Cllr Brian Dennehy
    Cllr Brian Dennehy
  • Jan 11, 2018
  • 1 min read

COMHAIRLE CONTAE FHINE GALL

FINGAL COUNTY COUNCIL

BALBRIGGAN/SWORDS AREA COMMITTEE MEETING

(Services B - Strategic & General Matters)

THURSDAY 11TH JANUARY 2018

ITEM 23

Question: Councillor B. Dennehy

"

Reply:

The Rush Sewerage Network Scheme is currently at commissioning /testing

stage. All 3 pump stations (South Shore/East Shore & North Beach) were put

into operation in mid-December. This initiates a 3 month proving period which

will end in mid-March. Thereafter a 12 month operation period will commence.

Therefore the Rush network is currently serviced by the Donabate/Portrane

Treatment Plant.